630,000 Pyeong First; Mass Production Target 2030
The Korea Land & Housing Corporation has begun designing the semiconductor national industrial complex and has put in place a special provision allowing site preparation and infrastructure work to proceed before the industrial complex designation is granted.
The plan is to supply 3.1 GW of power and 150,000 tons of water per day on a priority basis by the end of 2028. Initial water supply will use the existing water conveyance facilities, with only a roughly 1 km additional connection for the industrial complex section. For long-term water supply, the approach has been changed to building a new 59-meter-high dam. The government has asked the Ministry of National Defense to disperse the 1st Combat Air Wing's functions to other bases by the end of 2027, and is pursuing an amendment to the special act so that the relocation cost is covered by the national budget.