AI Data Center Construction Stalls Amid Infrastructure and Power Shortages
Permit delays caused by resident opposition and local government construction bans, combined with years needed to connect to the power grid, mean that half of the large projects announced this year are struggling to break ground. A market official said that the difficulty of securing electricity is the biggest problem. Backlogs in gas turbine supply for on-site power generation have also left half of this year's large projects still before construction.
Half of the large data center projects announced this year have not yet started construction due to permit delays, resident opposition, and shortages of equipment and electrical engineers. Grid connection can take years, and supply of gas turbines for on-site power is also backlogged.